The project consists of trenching, removing first isolator, sand blast and re-wrapping the first nationwide gas pipeline in Isfahan. Operation area was located in Mimeh, between km 465 to 480, and as the operation was done on active utilities, it had particular conditions.
Projects > Replacing Operation of 15km of First Nationwide Pipeline Coating (465-480Km)
View the embedded image gallery online at:
https://chakad.co/en/projects/chakad-projects/complete-projects/item/60-replacing-operation-of-15km-of-first-nationwide-pipeline-coating-465-480km.html#sigProId54698b670a
https://chakad.co/en/projects/chakad-projects/complete-projects/item/60-replacing-operation-of-15km-of-first-nationwide-pipeline-coating-465-480km.html#sigProId54698b670a
SPECIFICATION
- Employer: National Iranian Gas Co.
- Location: Isfahan
- Start Date: June 2004
- Finish Date: 06/07/2005