This project is to irrigate Dasht abbas agricultural lands by irrigation network from Karkhe dam. Right now, the water is directed to two pump station in Cheshme khosh and Chenaneh by constructed canals. This project is to procure, transport and installation of 230 km of G.R.P pipe with 400 to 2200mm diameter and 60 km PE pipe with 110 to 400 mm diameter and also several valves chamber. The Chakad co. as Chakad-Oztas Co. is performing all mechanical, civil and material purchase of the project.

SPECIFICATION

  • Employer: Ilam Regional Water Co.
  • Location: Ilam
  • Start Date: August 2006
  • Finish Date: 03/10/2016