Construction of mechanical, electrical and instrumentation of utility unit and storage area in Morvarid Petrochemical plant includes piping for an amount of approximately 90.000 inches in diameter , Pumps, compressors and other rotary and static equipment installation ,tanks ,steel structures, pipe rack ,implementation of electrical and instrumentation , test and commissioning.
Projects > Mechanical Installation of utility unit and storage area of 5th Olephin
SPECIFICATION
- Employer: Morvarid petrochemical company
- Location: Assaluyeh
- Start Date: 22/08/2008
- Finish Date: 27/01/2010